    Service instructions for heating engineers Vitoflame 100 Pressure−jet oil burner (type VE III) H for Vitoplex 100, 200 and 300 Rated output 80 to 225 kW H for Vitorond 200 Rated output 125 to 195 kW For applicability, see the last page.
  • Page 2: General Information

    General information Safety instructions ¨ Please follow these safety instructions closely to prevent accidents and material losses. Safety instructions explained Regulations ¨ Danger Observe the following when working This symbol warns against the on this system H all legal instructions regarding the risk of injury.

  • Page 3
    H Ventilate the boiler room. Replace faulty components H Close the gas shut−off valve. only with original Viessmann spare parts. Working on the heating system Ancillary components, spare and H Isolate the system from the power…
  • Page 4: Table Of Contents

    Capacity Index Page General information Safety instructions ……………………Initial start−up, inspection and maintenance Steps Initial start−up, inspection and maintenance .

  • Page 5: Initial Start−Up, Inspection And Maintenance

    Initial start−up, inspection and maintenance Steps Initial start−up, inspection and maintenance For further instructions on individual steps, see pages indicated. Commissioning steps Inspection steps Maintenance steps Page 1. Starting the heating system ……….2.

  • Page 6: Further Details Regarding The Individual Steps

    Initial start−up, inspection and maintenance Further details regarding the individual steps To obtain optimum combustion values, the burner must be adjusted with the boiler heated to operating temperature (min. 60 ºC). Also carry out measurements at base load. Starting the heating system Boiler control unit service instructions 1.

  • Page 7: Checking The Adjustment Of The Air Damper Servomotor

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Checking the adjustment of the air damper servomotor The burner is equipped with an air damper servomotor with adjustable switch cams used to position the air damper plus a solenoid valve control.

  • Page 8: Adjusting The Oil Pressure And Checking The Vacuum

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Adjusting the oil pressure and checking the vacuum The oil pressure is preset at the factory according to the oil throughput. Readjust the oil pressure, if required. 1. Switch OFF the mains isolator and safeguard against unauthorised reconnection.

  • Page 9
    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) 7. If required, adjust the oil pressure at pressure adjusting screw C for stage 1 and D for stage 2. ³ pressure rises Clockwise Anti−clockwise ³ pressure falls. For standard burner settings, see page 38.
  • Page 10: Adjusting The Air Volume

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Adjusting the air volume The air volume is preset at the factory. If required, adjust the air volume; for this, first adjust the air volume for stage 2 at the blast tube connection. Starting up the burner may require a fine adjustment.

  • Page 11
    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Readjusting stage 1 1. Change service switch B to position II (automatic mode) and close the flap. 2. Change the burner to stage 1 by pulling plug lÖ. 3.
  • Page 12: Cleaning And Checking The Flame Monitor

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning and checking the flame monitor Remove flame monitor A (photo resistance) from its retainer, whilst the burner is operating. The system should then perform a fault shutdown if the flame monitor is covered up.

  • Page 13: Cleaning The Burner

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning the burner 1. Set the burner into its Cleaning the combustion maintenance position. chamber and hot gas flues, see boiler service 2. Clean the casing, the flame tube, instructions.

  • Page 14: Replacing The Nozzle

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Replacing the nozzle 1. Remove sensor plate A from the blast tube connection. 2. Replace nozzle B (prevent the blast tube connection from turning); during this step prevent air bubbles from forming in the blast tube connection.

  • Page 15: Checking And Adjusting The Ignition Electrodes

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Checking and adjusting the ignition electrodes Check ignition electrodes A for wear, contamination and size (see fig.) and replace, if required. + 0.3 80 kW 14 mm (105 kW) 13 mm (90 kW) 12 mm (120, 130 and 150 kW) 5 mm (105 kW)

  • Page 16: Cleaning And Replacing The Oil Pump Filter, If Required

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning and replacing the oil pump filter, if required Danfoss oil pump, type BFP 52 A Filter plug B O−ring (replace) C Filter (replace) Suntec oil pump, type AT 2 55 A Filter (clean or replace)

  • Page 17: Operating And Service Documents

    Initial start−up, inspection and maintenance Further details regarding the individual steps (cont.) Operating and service documents 1. Complete and detach the 2. Keep all parts lists, operating and customer registration card: service instructions in the folder H Give the system user this part and hand this over to the system for safe−keeping.

  • Page 18: Burner Control Unit

    Initial start−up, inspection and maintenance Burner control unit Program sequence during commissioning 1 qW Plug−in terminals on the Start command B B’ Interval for flame to build burner control unit E Burner motor Burner operating position F Solenoid valve stage 2 achieved H Solenoid valve stage 1 Burner operation…

  • Page 19: Troubleshooting

    Troubleshooting Diagnostics Fault Cause Remedy Burner does not start No voltage Check the fuse in the control unit or in the plug−in panel; check the electrical connections, the position of the ON/OFF switch at the control unit and that of the mains isolator.

  • Page 20
    Troubleshooting Diagnostics (cont.) Fault Cause Remedy Pump does not supply oil Shut−off valves closed at Open valves filter or in oil pipe Filter blocked Clean filter (pre−filter and pump filter) Coupling between Replace coupling motor and pump faulty Suction pipe leaking Tighten connections.
  • Page 21
    Troubleshooting Diagnostics (cont.) Fault Cause Remedy Flame extinguishes Air in suction line Seal line and filter during operation Nozzle faulty Replace nozzle Air incorrectly adjusted; Adjust pre−settings pump pressure correctly (see page 38) incorrectly adjusted Interior of the sensor Clean the interior of the plate and flame tube sensor plate and flame contaminated…
  • Page 22: Components Overview

    Components overview Components overview Legend 1 Service switch (for burner qT Fan motor qZ Servomotor adjustment) 2 Hood adaptor qU Fan housing 3 Fixing plate for burner hood qI Inlet air silencer qO Impeller adaptor 4 Quick−acting closure wP Air regulating valve 5 Ignition transformer wQ Flame monitor 6 Burner control unit…

  • Page 23
    Components overview Components overview (cont.) qP + qE +…
  • Page 24: Connection And Wiring Diagrams

    Connection and wiring diagrams Connection and wiring diagram Flame monitoring through photo resistance 6.3A (slow) 250V Jumper…

  • Page 25: H Flame Monitoring Through Light Flicker Detector

    Connection and wiring diagrams Connection and wiring diagram (cont.) Flame monitoring through light flicker detector 6.3A (slow) 250V Jumper…

  • Page 26
    Connection and wiring diagrams Connection and wiring diagram (cont.) Note This wiring diagram only applies in conjunction with Viessmann products. A Control unit components Burner plug on control unit 90 D B Burner control unit Internal connection with plug−in connector lÖ…
  • Page 27: Parts List

    Parts list Parts list When ordering spare parts: 065 Solenoid valve nut for oil pump Quote the type and serial no. (see (Suntec) type plate) and the item no. of the 081 Strapping plug no. 121 required part (as per this parts list). 082 Fuse 4 A/250 V (slow) Obtain standard parts from your 085 Silencer hood…

  • Page 28
    Parts list Parts list (cont.) 003 Small parts comprising: Parts not shown 3a Cheese−head screw M 6 × 16 051 Allen grub screw SW 5 3b Cheese−head screw M 6 × 10 052 Burner housing pack 3c Serrated washer A 6.4 053 Installation instructions 3d Twin clip 18 ×…
  • Page 29
    Parts list Parts list (cont.)
  • Page 30
    Parts list Parts list (cont.)
  • Page 31
    Parts list Parts list (cont.)
  • Page 32
    Parts list Parts list (cont.)
  • Page 33
    Parts list Parts list (cont.)
  • Page 34
    Parts list Parts list (cont.)
  • Page 35: Appendix

    Appendix Specification In conjunction with Vitoplex 100 and Vitoplex 300 Rated boiler output Burner output 61/87 80/115 99/142 130/186 171/245 Stage 1/2* Burner type VE III 1 VE III 2 VE III 2 VE III 3 VE III 4 Type test no. 5 G 399/ 5 G 400/ 5 G 400/…

  • Page 36
    Appendix Specification (cont.) In conjunction with Vitoplex 200 Rated boiler output Burner output 68/97 91/130 114/163 152/217 Stage 1/2* Burner type VE III 2 VE III 2 VE III 3 VE III 4 Type test no. 5 G 399/ 5 G 400/ 5 G 400/ 5 G 422/ to EN 267…
  • Page 37
    Appendix Specification (cont.) In conjunction with Vitorond 200 Rated boiler output Burner output 95/136 122/174 149/213 Stage 1/2* Burner type VE III 2 R VE III 3 R VE III 4 R Type test no. 5 G 400/04 S 5 G 421/05 S 5 G 422/05 S to EN 267 Voltage Frequency…
  • Page 38: Standard Burner Settings

    Appendix Standard burner settings Note Check that the service instructions are valid for the burner concerned (see notes on applicability, page 44 and serial no. on the burner type plate). In conjunction with Vitoplex 100 and Vitoplex 300 Rated output Oil burner nozzle Make Delavan…

  • Page 39
    Appendix Standard burner settings (cont.) In conjunction with Vitoplex 200 Rated output Oil burner nozzle Make Delavan Type 60º B 60º B Fluidics Type 60º H Steinen Type 60º H 1.75 2.25 2.75 3.25 Oil pressure approx. Stage 1 bar min. Stage 2 18.5 Oil flow rate…
  • Page 40
    Appendix Standard burner settings (cont.) In conjunction with Vitorond 200 Rated output Oil burner nozzle Make Delavan Type 60º W 60º W 60º W 2.00 2.75 3.25 Oil pressure approx. Stage 1 bar min. Stage 2 Oil flow rate Stage 1 kg/h 10.3 12.4…
  • Page 41: Commissioning/Service Report

    Appendix Commissioning/service report Setting and test values Initial start−up Maintenance/ service Oil pressure H Stage 1 actual H Stage 2 actual Vacuum actual after maint. Smoke spot number H Stage 1 actual after maint. H Stage 2 actual after maint. Carbon dioxide content CO H Stage 1 % by vol.

  • Page 42
    Appendix Commissioning/service report (cont.) Setting and test values Initial start−up Maintenance/ service Flue gas loss H Stage 1 actual H Stage 2 actual Draught (at the boiler back) actual Blast tube connection actual setting actual Air damper setting Position of the switch cams at the air damper servomotor º…
  • Page 43: Keyword Index

    Appendix Keyword index Adjusting the air volume, 10 Parts list, 27 Applicability, 44 Safety instructions, 2 Burner cleaning, 13 Specification, 35 Standard burner settings, 38 Starting the system, 6 Commissioning/service report, 41 Steps, 5 Components overview, 22 Connection and wiring diagrams, 24 Troubleshooting, 19 Diagnostics, 19 Vacuum, checking, 8…

  • Page 44: Applicability

    Applicability from serial no. 7188626 5 00001 kkk, 7188627 5 00001 kkk, 7188628 5 00001 kkk and 7188629 5 00001 kkk Viessmann Werke GmbH & Co KG D 35107 Allendorf Tel: +49 6452 70 0 Fax: +49 6452 70 27 80 www.viessmann.de…

(Ocr-Read Summary of Contents of some pages of the Viessmann Vitoflame 100 Document (Main Content), UPD: 03 August 2023)

  • 2, Viessmann Vitoflame 100 2 General information Safety instructions Please follow these safety instructions closely to prevent accidents and material losses. Work on the equipment Installation, initial start-up, inspection, maintenance and repairs must only be carried out by a competent person (heating engineer/installation contractor). Before working on the equipment/ heating system, isolate the mains electrical supply (e.g. by removing a separate mains fuse or by means of a mains electrical isolator) and safeguard against unauthorised reconnection. Close the m…

  • 56, 56 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Static pressure mbar max.Ă50Ămbar Supply pressure (flow pressure) j for natural gas E mbar 20ĂĆĂ25 mbar j for natural gas LL mbar 20ĂĆĂ25 mbar tick gas type Nozzle pressure Stage 1 located mbar p set mbar see table on Stage 2 located mbar see table on page 47 set mbar Ionisation current located mA min 5µA…

  • 18, 18 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking air pressure switch At the factory, the air pressure switch is adjusted to the corresponding switching point, so that readjustment is generally not required. However, should an adjustment nevertheless be required, check the air pressure switch setting and correct, if required, in accordance with the details below by rotating black scaled ring B. A Adjustment…

  • 21, 21 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking ignition and ionisation electrodes 90 to 100 kW 125 to 210 kW A Earth electrode B Sensor plate C Ionisation electrode D End plate E Ignition electrode F 8 gas orifices in end plate G Slightly turn the ionisation electrode in accordance with the gap towards the earth electrode H Direct the tip of the ignition electrode towards the edge of the gas orifice 5692Ă534ĂGB

  • 28, 28 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner does not start, demand lamp does not illuminate No voltage present Check fuse in control unit and in plug-in terminal block, check electrical connections, position of the ON/OFF switch on control unit and mains electrical isolator High limit safety cut-out activated Press reset button on boiler control unit Vitoair motor faulty Replace Vitoair motor Fuse in leak detector device blown Replace fuse Fault during leak t…

  • 12, 12 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking nozzle pressure 1. Release the screw in test nippleĂA but do not remove. 2. Connect the U-shaped pressure gauge to test nippleĂA. 3. Open the gas shut-off valve. 4. Start up the burner (see page 8). 5. Check the nozzle pressure in accordance with the Wobbe index and the output rating in the nozzle pressure table on pageĂ47. Please note: During t…

  • 20, Viessmann Vitoflame 100 20 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning gas orifices in sensor plate (if necessary) 1. Pull the leads from electrodesĂH andĂG. 2. Loosen electrode holdersĂK andĂA, and remove the ignition and ionisation electrodes. 3. Remove the nut from earth electrodeĂF and unscrew the electrode. 4. Unscrew the Allen screws from sensor plateĂE. 5. Remove sensor plateĂE, spring washerĂD and end plateĂC from mixer assemblyĂB and clean. 6. Assemble in reverse order. Please …

  • 9, 9 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking adjustment of air damper actuator The burner is equipped with an air damper actuator motor with adjustable switching cams for setting the air damper position and for switching the solenoid valves. During a regular shutdown, the burner air damper will drive into the «closed» position. This reduces cooldown losses. The switching cams are located below…

  • 30, 30 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner starts up, but no flame is formed 2Ă× Insufficient combustible gas mixture available Vent gas supply line to the outside. Check with a test burner, whether sufficient combustible gas is available. 2Ă× Gas solenoid valves fail to open Check electrical connection, voltage across gas train (230 V). Replace gas train if voltage is present at valve. Burner starts up and ignition is OK, but burner enters a fault 2Ă× Start gas volume poorly adjusted…

  • 29, 29 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner does not start (demand 3Ă× Burner motor faulty Replace burner motor ( lamp illuminates) Actuator faulty (zero volt at terminal 4) Replace actuator Burner does not run and goes into a fault state after approx. 65 s 4Ă× Air pressure switch Check air pressure switch settings and replace switch if necessary pp 4Ă× Earth connection at ionisation cable or elect…

  • 27, 27 Troubleshooting Diagnostics (cont.) Diagnosis of fault causes Fault code table (red fault lamp) Fault Possible cause 2 x flashing The flame is not established at the end of the safety period 3 x flashing Air pressure switch does not close during pre-purge 4 x flashing Air pressure switch does not open or external light at burner start (after 65 s) 5 x flashing External light during pre-purge or internal device fault 7 x flashing Flame tears off during operation 8 … 17 x flas…

  • 19, 19 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning burner 1. Set the burner to maintenance. 2. Clean housingĂC, flame tubeĂA, mixer assemblyĂB and impellerĂD. For cleaning the combustion chamber and hot gas flues, see boiler service instructions. 3. Check the gas orifices in the sensor plate for contamination and clean, if required (seeĂpageĂ20). 4. Check the tightne…

  • 64, 64 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Oxygen content O Stage 1 located % by vol. yg O 2 set % by vol. Stage 2 located % by vol. set % by vol. Carbon monoxide content CO located ppm content CO relative to 0Ă% oxygen content set ppm Gross flue gas Stage 1 located ºĂC g temperature set ºĂC Stage 2 located ºĂC set ºĂC Flue gas loss Stage 1 located % g set % Stage 2 located % set % Draught (at the locate…

  • 15, 15 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Air volume adjustment The air volume is preset at the factory. If necessary, readjust the air volume, first adjusting the air volume for stageĂ2. Fine adjustment stageĂ2 Adjust the air volume at adjusting screwĂA to modify the mixer assembly: H Anti-clockwise Ălarger cross-section Ămore air, H Clockwise �…

  • 22, Viessmann Vitoflame 100 22 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking both valves of the gas train for leaks Please note: Only a function test is required for gas trains with leak test device. 1. Close the gas shut-off valve. 2. Release the screw in test nippleĂA but do not remove. 3. Release the screw in test nippleĂB but do not remove. 4. Connect the U-shaped pressure gauge with a manual pump to test nippleĂB. 5. By gently activating the manual pump, create a test p…

  • 14, 14 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Adjusting start-up gas volume The opening characteristics of the gas solenoid valve have been matched to the boiler and been preset at the factory. Generally you do not need to change this setting. 1. Set the quick-action (opening characteristics) with protective capĂGĂinverted. Please note: At the factory, the quick-…

  • 16, 16 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Fine adjustment stageĂ1 1. Set service switchĂB to positionĂII (automatic mode), and close the cover flap. 2. Change the burner over to stageĂ1 by pulling plug lÖ. 3. Remove the actuator motor cover. 4. Modify the air volume by turning the adjusting screw on switching camsĂSTĂ1 (see fig. on pageĂ9): H ClockwiseĂĂmore air, H Anti-clockwiseĂĂless air. Please note: Adjust switching cam…

  • 38, Viessmann Vitoflame 100 38 Connection and wiring diagrams Connection and wiring diagram (cont.) 5692Ă534ĂGB . Control Control unit components Actuator Actuator Control burner stage 2 hours run counter stage 2 external Fuel valve 2 Burner motor Control demand stage 1 stage 2 Control demand Actuator Fuel valve 2 Burner motor (slow) (slow) unit components

  • 37, Viessmann Vitoflame 100 37 Connection and wiring diagrams Connection and wiring diagram Legend 11 Ionisation monitoring 36 Fuel valve 2 54 Ignition transformer 100 Burner motor 111 Strapping plug 122 Actuator 123 Actuator 126 Service switch 129 Fuel valve 1 130 Gas governor 131 Air pressure switch fA Burner plug on control unit 90 D Internal connection inside plug-in connector lÖ F Ă1 Fuse in plug-in module TR/STB Safety equipment inside control un…

  • 10, 10 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking static and supply pressure Check the type of gas with your local gas supplier. The burner is factory-set to natural gas E. Adjust the nozzle pressure for operation with natural gas LL according to the table on pageĂ47. Record the gas type in the service report on page 50. Static pressure 1. Close the gas shut-off valve. 2. …

  • 4, 4 Initial start-up, inspection and maintenance StepsĂćĂinitial start-up, inspection and maintenance For further instructions on individual steps, see pages indicated. Commissioning steps Inspection steps Maintenance steps Page C 1. Commissioning preparationsĂ 6. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C I M 2. System start-upĂ 8. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . …

Similar Devices: PUREWELL VariHeat he, ULTIMATE 30BF, EuroStar WM 50

  • Appr. nr. B98.01 A — CE 0063 AT 4967INSTALLATION, SERVICE AND USER INSTRUCTIONSFERROLI F24gas combination boiler for central heatingand hot water production, wall mounted,copper heat exchanger, fan assisted,room sealed, electronic fl ame ignition and controlcod. 3544015/2 — 05/2005G.C. NO: 47-267-31 …

    F24, 52

  • When replacing any part on this appliance, use only spare parts that you can be assured conform to the safety and performance specification that we require. Do not use reconditioned or copy parts that have not been clearly authorised by Ideal Boilers.For the very latest copy of literature for specification and maintenance practices visit our website www.id …

    114453, 8

  • NBE PELLET SYSTEMS RTB Ready to Burn EN303-5 2012 Class 5 approved by DTI. Approved for expansion vessel. Energy class AA. Manufacturer: NBE Production A/S Brinken 6-10 Øster Vrå Denmark www.nbe.dk …

    RTB, 29

  • A MP+ 1.115 — 1.130 — 1.150it CALDAIA MURALE A GAS A CONDENSAZIONEManuale per l’uso destinato all’utente e all’installatoreen CONDENSING GAS WALL-HUNG BOILERS,QVWUXFWLRQVPDQXDOIRUXVHUVDQG¿WWHUVde (AT) KONDENSATIONS-WANDGASHEIZKESSEL Gebrauchsanleitung für den Benutzer und Installateures CALDERA MURAL DE GAS A CONDENSACIÓNManu …

    LUNA DUO-TEC MP+ 1.115, 39

  • Installation, Operation and Maintenance Instructions Document 1187BInstallation,Operation andMaintenanceInstructions forEnduranceEBP Series Modulating Combination Boiler(natural or propane gas)EDP Series Modulating Hydronic Boiler(natural or propane gas)EDN Series Modulating Boiler, non ferrous(natural or propane gas)WARNINGIf the information in this manual …

    EBP0110, 40

  • To be retained by householderUSER, INSTALLATIONCOMMISSIONING & SERVICINGINSTRUCTIONSBALANCED FLUEOIL FIRED CENTRAL HEATING BOILERSTRIANCOEuroStar WM 50/65In The Wall BoilerBED 92/42 EECEMC 89/336 EEC …

    EuroStar WM 50, 28

Table of Contents: Viessmann Vitoflame 100 Burner Owner’s Manual

  • Viessmann Vitoflame 100 3 Contents Index Page General information Safety instructionsĂ 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ApplicabilityĂ 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

  • 53 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 48 Appendix Standard values for burner settings (cont.) Mixer setting Rated output range from kW to kW 90 100 125 140 150 165 190 210 Boiler output kW 90 100 125 140 150 165 190 210 Standard values for mixer setting mm 8.0 10.5 14.0 17.0 18.5 21.0 18.0 22.0 Gas throughput subject to the operational net calorific value (H uB ) Gas type Gas group Operational net calorific value H UB G as t ype G as group O pera ti ona l ne t ca l or ifi c va l ue H UB kWh/m 3 MJ/m 3 Natural gas E 9.45 34.02 Natural gas LL 8.13 29.25 Gas Gas Rated boiler output G as G as R a t e d b o il er ou t pu t type grou

  • Viessmann Vitoflame 100 55 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • 38 Connection and wiring diagrams Connection and wiring diagram (cont.) 5692Ă534ĂGB . Control Control unit components Actuator Actuator Control burner stage 2 hours run counter stage 2 external Fuel valve 2 Burner motor Control demand stage 1 stage 2 Control demand Actuator Fuel valve 2 Burner motor (slow) (slow) unit components

  • 9 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking adjustment of air damper actuator The burner is equipped with an air damper actuator motor with adjustable switching cams for setting the air damper position and for switching the solenoid valves. During a regular shutdown, the burner air damper will drive into the «closed» position. This reduces cooldown losses. The switching cams are located below the air damper actuator motor cover. A scaling ring is locat

  • Viessmann Vitoflame 100 60 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Output located kW set kW Switch cam ii h i ST 1 located º position at the air damper actuator set º d amper ac t ua t or ST 2 located º set º MV located º set º Static burner Stage 1 located mbar pressure set mbar Stage 2 located mbar set mbar Mixer assembly located ring no. y set ring no. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 64 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Oxygen content O Stage 1 located % by vol. yg O 2 set % by vol. Stage 2 located % by vol. set % by vol. Carbon monoxide content CO located ppm content CO relative to 0Ă% oxygen content set ppm Gross flue gas Stage 1 located ºĂC g temperature set ºĂC Stage 2 located ºĂC set ºĂC Flue gas loss Stage 1 located % g set % Stage 2 located % set % Draught (at the located hPa g( boiler end) set hPa 5692Ă534ĂGB

  • Viessmann Vitoflame 100 8 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) To obtain the optimum combustion values, it is essential to adjust the burner with the boiler heated to operating temperature (min. 60ĂºC). Also carry out measurements at base load. System start-up Service instructions Boiler control unit. 1. Check the heating system pressure. 2. Open the gas shut-off valve. 3. Check the supply pressure (see page 11). 4. Switch ON the mains electrical isolator (outside the boiler ro

  • 18 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking air pressure switch At the factory, the air pressure switch is adjusted to the corresponding switching point, so that readjustment is generally not required. However, should an adjustment nevertheless be required, check the air pressure switch setting and correct, if required, in accordance with the details below by rotating black scaled ring B. A Adjustment ma

  • Viessmann Vitoflame 100 11 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Supply pressure ĂĂ7. Start the burner. Please note: Initial start-up, see pageĂ8. Switch the burner to stage 2. To do this, activate the emissions test switch on the control unit. ĂĂ8. Check the supply pressure (flow pressure), see the table below. Please note: The supply pressure (flow pressure) should be between 20 and 25Ămbar. The gas governor is factory-set to 12.5 mbar. Do not change this setting. ĂĂ9. Record the actual values in the commissioning report on page 50. 10. Close the gas shut-off valve. 11. Remove the

  • 44 Parts list Parts list (cont.) 5692Ă534ĂGB

  • Viessmann Vitoflame 100 20 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning gas orifices in sensor plate (if necessary) 1. Pull the leads from electrodesĂH andĂG. 2. Loosen electrode holdersĂK andĂA, and remove the ignition and ionisation electrodes. 3. Remove the nut from earth electrodeĂF and unscrew the electrode. 4. Unscrew the Allen screws from sensor plateĂE. 5. Remove sensor plateĂE, spring washerĂD and end plateĂC from mixer assemblyĂB and clean. 6. Assemble in reverse order. Please note: Observe the correct orientation of the gas orifices in the end plate (see page 21). 5692Ă534Ă

  • 17 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking ionisation current 1. Switch OFF the system ON/OFF switch. 2. Separate the plug connection of the ionisation current cable (red cable). Please note: When checking with a TestomatikĆGas, test cable no.Ă1 is required. You can also carry out this check with a multimeter. 3. Switch ON the system ON/OFF switch. Please note: The system then initiates a fault shutdown. 4. Press the reset button at the burner control unit and switch OFF the system ON/OFF

  • Viessmann Vitoflame 100 39 Connection and wiring diagrams Connection and wiring diagram (cont.) 5692Ă534ĂGB Jumper up to from Burner control unit Gas governor Fuel valve 1 Hours run counter stage 1 external Air pressure switch Ignition transformer Flame monitor External fault message Flame monitor Ignition transformer Air pressure switch Fuel valve 1Gas governor

  • Viessmann Vitoflame 100 6 Initial start-up, inspection and maintenance Further details regarding the individual steps Commissioning preparations Leak test 1. Close the gas shut-off valve. 2. Loosen the screw in test nipple A but do not remove. 3. Connect the pressure test equipment to test nipple A. 4. By gently activating the manual pump, create a test pressure of approx. 100 mbar. 5. Wait approx. 5 minutes for the temperature to level out, then observe the pressure gauge display: The test area is free from leaks, if the display pressure does not fall by more than 1 mbar within a further five minutes. ¨ĂSafety instruction Chec

  • Viessmann Vitoflame 100 22 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking both valves of the gas train for leaks Please note: Only a function test is required for gas trains with leak test device. 1. Close the gas shut-off valve. 2. Release the screw in test nippleĂA but do not remove. 3. Release the screw in test nippleĂB but do not remove. 4. Connect the U-shaped pressure gauge with a manual pump to test nippleĂB. 5. By gently activating the manual pump, create a test pressure of approx. 50 mbar. 6. Wait approximately five minu

  • Viessmann Vitoflame 100 45 Parts list Parts list (cont.) 5692Ă534ĂGB

  • Viessmann Vitoflame 100 32 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Combustion errors through pulsation Start gas volume too large or too small Adjust start gas volume or opening characteristics (see page 14) p Flue gas draught incorrect Check flue gas draught (chimney) CO is formed or burner is very sooty Too little or too much air Correct setting. Check boiler room ventilation. CO 2 content too low or O 2 content too high Incorrect setting Adjust nozzle pressure in accordance with type of gas used. Correct air damper setting. Infiltrating ai

  • 23 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking filter insert of gas train (make: Dungs) 1. Close the gas shut-off valve. 2. Unscrew filter lidĂD. 3. Withdraw filter elementĂB. 4. If necessary, clean or replace the filter element. 5. Replace filter lid gasketĂC. 6. Secure filter lidĂD. 7. Check the breather hole in plugĂA and clean if necessary. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 25 Troubleshooting Diagnostics Function sequence (see diagram on page 38 and 39): A Start command Startup by thermostat tw Delay: approx. 8 s Air pressure switch and flame relay are checked for correct contact position. t10 Default time for air pressure signal: min. 5 s After expiry of this delay, the set air pressure should be established, otherwise there will be a fault shutdown. t1 Pre-purge time: min. 30 s Purging the combustion chamber and the secondary heating surfaces. t3 Pre-ignition time: approx. 2 s During the pre-ignition time until the expiry of safety time t2, the flame relay is forcibly pulled up. Fuel is released afte

  • 41 Parts list Parts list Parts not shown 051 Allen key SWĂ5 052 Burner housing pack 053 Installation instructions 054 Operating instructions 055 Service instructions Wear parts 029 Ionisation electrode 030 Ignition electrode 037 Filter element 072 Earth electrode 003 Small parts comprising: 3a Cheese-head screw MĂ6Ă×Ă16 3b Cheese-head screw MĂ6Ă×Ă10 3c Serrated washer AĂ6.4 3d Cable grommet 3e Double pipe clip 12Ă×Ă12 mm 3f Cheese-head screw MĂ4Ă×Ă8 3g Serrated washer AĂ4.3 3h Cheese-head screw MĂ6Ă×Ă10 3i Nut MĂ5 3j Coun

  • Viessmann Vitoflame 100 13 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Please note: Never turn the pressure regulator outside its setting range. Turn set screw F only as long as the nozzle pressure noticeably changes. Main volume butterfly D should be turned fully to «+». Adjusting stage 2 Please note: Start the burner in stage 2. To do this, activate the emissions test switch on the control unit. Service switch B must be in position II. ĂĂ7. Move the cover over both sides of adjusting screw Fā. ĂĂ8

  • Viessmann Vitoflame 100 7 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Function test without gas supply H Check the function sequence (see function diagram on page 25). H Switch ON the mains electrical isolator (outside the boiler room). H Start the burner. To do this, switch ON the ON/OFF switch at the control unit. H With the leak test equipment still connected, build the pressure to approx. 20Ămbar (gas shut-off valve closed). The following program must now run (see also the function diagram on page 25): If a heat demand is present (Ă»demand» lamp at the plug-in

  • Viessmann Vitoflame 100 59 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • 12 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking nozzle pressure 1. Release the screw in test nippleĂA but do not remove. 2. Connect the U-shaped pressure gauge to test nippleĂA. 3. Open the gas shut-off valve. 4. Start up the burner (see page 8). 5. Check the nozzle pressure in accordance with the Wobbe index and the output rating in the nozzle pressure table on pageĂ47. Please note: During the adjustment, also check the gas throughput by means of a volumetric test. 6. Check and, if necessary,

  • Viessmann Vitoflame 100 46 Appendix Specification Rated output range from kW to kW 90 100 125 140 150 165 190 210 Boiler output kW 90 100 125 140 150 165 190 210 Burner output 1 st /2 nd Ăstage* 1 kW 59/ 98 65/ 109 82/ 136 91/ 152 98/ 163 107/ 179 124/ 207 137/ 228 Type of burner VGĂIIIĆ2 VGĂIIIĆ3 VGĂIIIĆ4 VGĂIIIĆ5 Product ID CEĆ0085 AQ 0222 Voltage V 230 Frequency Hz 50 Power consumption W 200 250 340 390 Motor speed rpm 2800 Version Two stage Gas supply pressure mbar 20 Gas connection GĂ(cyl.Ăfem.Ăāthread) 1″ 1¼» *1 Corresponds to the boiler rated thermal load. 5692Ă534ĂGB

  • 54 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Initial start-up Output located kW set kW Switch cam ii h i ST 1 located º position at the air damper actuator set º d amper ac t ua t or ST 2 located º set º MV located º set º Static burner Stage 1 located mbar pressure set mbar Stage 2 located mbar set mbar Mixer assembly located ring no. y set ring no. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 49 Appendix Standard values for burner settings (cont.) Gas throughput subject to the operational net calorific value (H uB ) (cont.) Gas Gas Rated boiler output G as G as R a t e d b o il er ou t pu t type group 150 to 165 kW 190 to 210 kW yp gp Boiler output 150 kW 165 kW 190 kW 210 kW m 3 /h l/min m 3 /h l/min m 3 /h l/min m 3 /h l/min Natural E 17.3 289 19.0 318 21.9 366 24.2 405 Natural gas LL 20.1 336 22.1 370 25.4 424 28.1 470 Please note: Partial load gas throughput equals 60Ă% of full load gas throughput. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 66 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Output located kW set kW Switch cam ii h i ST 1 located º position at the air damper actuator set º d amper ac t ua t or ST 2 located º set º MV located º set º Static burner Stage 1 located mbar pressure set mbar Stage 2 located mbar set mbar Mixer assembly located ring no. y set ring no. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 2 General information Safety instructions Please follow these safety instructions closely to prevent accidents and material losses. Work on the equipment Installation, initial start-up, inspection, maintenance and repairs must only be carried out by a competent person (heating engineer/installation contractor). Before working on the equipment/ heating system, isolate the mains electrical supply (e.g. by removing a separate mains fuse or by means of a mains electrical isolator) and safeguard against unauthorised reconnection. Close the main gas shut-off valve and safeguard against unauthorised reopening. Work

  • Viessmann Vitoflame 100 50 Appendix Commissioning/service report Setting and test values Date: By: Set value Initial start-up Static pressure mbar max.Ă50Ămbar Supply pressure (flow pressure) j for natural gas E mbar 20ĂĆĂ25 mbar j for natural gas LL mbar 20ĂĆĂ25 mbar tick gas type Nozzle pressure Stage 1 located mbar p set mbar see table on Stage 2 located mbar see table on page 47 set mbar Ionisation current located mA min 5 µA set mA min. 5 µA Carbon dioxide CO Stage 1 located % by vol. content CO 2 set % by vol. Stage 2 located % by vol. set % by vol. 5692Ă534ĂGB

  • Viessmann Werke GmbHĂ&ĂCo DĆ35107 Allendorf Tel: +49 6452 70Ć0 Fax: +49 6452 70Ć27Ă80 www.viessmann.de Viessmann Limited Hortonwood 30, Telford Shropshire, TF1 7YP, GB Tel: +44 1952 675000 Fax: +44 1952 675040 email: [email protected] 68 Appendix Keyword index A Air damper actuator (checking settings),ă9 Air volume adjustment,ă15 Applicability,ă2 B Burner cleaning,ă19 Burner control unit,ă26 C Commissioning preparations,ă6 Commissioning/service report,ă50 Component summary,ă34 Connection and wiring diagrams,ă37 Conversion to natural

  • 14 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Adjusting start-up gas volume The opening characteristics of the gas solenoid valve have been matched to the boiler and been preset at the factory. Generally you do not need to change this setting. 1. Set the quick-action (opening characteristics) with protective capĂGĂinverted. Please note: At the factory, the quick-action is fully set to «+». Ionisation current at least 5 mA. Check the ionisation

  • Viessmann Vitoflame 100 63 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 30 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner starts up, but no flame is formed 2Ă× Insufficient combustible gas mixture available Vent gas supply line to the outside. Check with a test burner, whether sufficient combustible gas is available. 2Ă× Gas solenoid valves fail to open Check electrical connection, voltage across gas train (230 V). Replace gas train if voltage is present at valve. Burner starts up and ignition is OK, but burner enters a fault 2Ă× Start gas volume poorly adjusted Adjust start gas volume or opening character

  • Viessmann Vitoflame 100 15 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Air volume adjustment The air volume is preset at the factory. If necessary, readjust the air volume, first adjusting the air volume for stageĂ2. Fine adjustment stageĂ2 Adjust the air volume at adjusting screwĂA to modify the mixer assembly: H Anti-clockwise Ălarger cross-section Ămore air, H Clockwise Ăsmaller cross-section Ăless air. 5692Ă534ĂGB

  • 43 Parts list Parts list (cont.) 5692Ă534ĂGB

  • 58 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Oxygen content O Stage 1 located % by vol. yg O 2 set % by vol. Stage 2 located % by vol. set % by vol. Carbon monoxide content CO located ppm content CO relative to 0Ă% oxygen content set ppm Gross flue gas Stage 1 located ºĂC g temperature set ºĂC Stage 2 located ºĂC set ºĂC Flue gas loss Stage 1 located % g set % Stage 2 located % set % Draught (at the located hPa g( boiler end) set hPa 5692Ă534ĂGB

  • 61 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 56 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Static pressure mbar max.Ă50Ămbar Supply pressure (flow pressure) j for natural gas E mbar 20ĂĆĂ25 mbar j for natural gas LL mbar 20ĂĆĂ25 mbar tick gas type Nozzle pressure Stage 1 located mbar p set mbar see table on Stage 2 located mbar see table on page 47 set mbar Ionisation current located mA min 5µA set mA min. 5µA Carbon dioxide CO Stage 1 located % by vol. content CO 2 set % by vol. Stage 2 located % by vol. set % by vol. 5692Ă534ĂGB

  • 67 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 28 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner does not start, demand lamp does not illuminate No voltage present Check fuse in control unit and in plug-in terminal block, check electrical connections, position of the ON/OFF switch on control unit and mains electrical isolator High limit safety cut-out activated Press reset button on boiler control unit Vitoair motor faulty Replace Vitoair motor Fuse in leak detector device blown Replace fuse Fault during leak test (fault lamp illuminates) Check gas pressure nipple of gas train

  • 33 Troubleshooting 5692Ă534ĂGB

  • Viessmann Vitoflame 100 26 Troubleshooting Diagnostics (cont.) Burner control unit H in fault state, red fault lamp C illuminates constantly — Diagnosis of fault causes: — wait at least 10 s — press reset button B for at least 3 s. — read the flashing code of the fault lamp (see fault table). — after every flashing code a break of approx. 3 s — reset, i.e. press reset button B 0.5Ăto 3 s long. H operational, green signal lamp A illuminates constantly — press reset button B 0.5 to 3 s long when a code flashes to reinstate system operation. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 37 Connection and wiring diagrams Connection and wiring diagram Legend 11 Ionisation monitoring 36 Fuel valve 2 54 Ignition transformer 100 Burner motor 111 Strapping plug 122 Actuator 123 Actuator 126 Service switch 129 Fuel valve 1 130 Gas governor 131 Air pressure switch fA Burner plug on control unit 90 D Internal connection inside plug-in connector lÖ F Ă1 Fuse in plug-in module TR/STB Safety equipment inside control unit K.. Burner relay contact 1 Ć qW Plug-in terminals on burner control unit A Start command B — B` Interval for flame to be established C Burner operating position achiev

  • 36 Component summary 5692Ă534ĂGB

  • 40 Parts list Parts list When ordering spare parts Quote the type and serial no. (see type plate) and the item no. of the required part (as per parts list). Obtain common parts from your local supplier. Parts 002 Blast tube 003 Small parts comprising: see below 004 Blast tube fixing screw 005 Mixer assembly 006 Burner flange seal ring 007 Air pressure switch 008 Fan motor 009 Hose 010 Impeller 011 Seal ring 012 Gasket set 016 Air regulating damper 017 Burner hood 018 Cover 028 Sensor plate 031 Fuse 032 Ignition transformer 033 Burner control unit 034 Plug-in terminal block

  • 47 Appendix Standard values for burner settings Please note: Check that the service instructions are valid for the burner concerned (see notes on applicability, pageĂ2 and serial no. on the burner type plate). Nozzle pressure table Gas type Gas group Wobbe index Supply pressure yp gp Wo pp y p kWh/m 3 MJ/m 3 mbar *1 Natural gas E 15.00 54.00 20.0 Natural gas LL 12.40 44.60 20.0 Gas Gas Rated boiler output in kW G as G as R a t e d b o il er ou t pu t i n kW type group 90 ć 100 125 ć 140 150 ć 165 190 ć 210 Boiler output

  • 4 Initial start-up, inspection and maintenance StepsĂćĂinitial start-up, inspection and maintenance For further instructions on individual steps, see pages indicated. Commissioning steps Inspection steps Maintenance steps Page C 1. Commissioning preparationsĂ 6. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C I M 2. System start-upĂ 8. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C I M 3. Checking adjustment of the air dampe

  • Viessmann Vitoflame 100 19 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Cleaning burner 1. Set the burner to maintenance. 2. Clean housingĂC, flame tubeĂA, mixer assemblyĂB and impellerĂD. For cleaning the combustion chamber and hot gas flues, see boiler service instructions. 3. Check the gas orifices in the sensor plate for contamination and clean, if required (seeĂpageĂ20). 4. Check the tightness of flame tubeĂA and impellerĂD. 5692Ă534ĂGB

  • Viessmann Vitoflame 100 VitoflameĂ100 gas burner fitted to VitoplexĂ100 Service instructions for heating engineers VitoflameĂ100 Pressure jet gas burner (typeĂVGĂIII) for VitoplexĂ100 Rated output 90 to 210ĂkW See notes on applicability, pageĂ2. VITOFLAME 100 5692Ă534ĂGBăăă5/2003 Please keep safe

  • Viessmann Vitoflame 100 34 Component summary Component summary A Gas train B Service switch for burner settings C Hood adaptor D Quick-action fastener E Actuating motor F Air pressure switch G Fan motor H Reset button K Burner control unit L Ignition transformer M Ball shut-off valve N Flange O Air regulating damper P Burner housing R Fan impeller S Inlet air silencer T Blast tube U Ignition electrode V Sensor plate W Ionisation electrode X Mixer assembly 5692Ă534ĂGB

  • Viessmann Vitoflame 100 24 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking all gas unions for leaks 1. Insert new gaskets in all gas unions that have been opened. 2. Open the gas shut-off valve. 3. Check the inlet seals of the gas train for leaks. 4. Start up the burner (see page 8). 5. Check the outlet seals of the gas train for leaks. Implementing final tests 1. Implement all tests in the order of the commissioning report. 2. Record the actual values in the commissioning report on page 50. Please note: The flue pipe must be sealed at the boiler

  • 10 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking static and supply pressure Check the type of gas with your local gas supplier. The burner is factory-set to natural gas E. Adjust the nozzle pressure for operation with natural gas LL according to the table on pageĂ47. Record the gas type in the service report on page 50. Static pressure 1. Close the gas shut-off valve. 2. Loosen the screw in test nippleĂA but do not remove. 3. Connect t

  • Viessmann Vitoflame 100 51 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 16 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Fine adjustment stageĂ1 1. Set service switchĂB to positionĂII (automatic mode), and close the cover flap. 2. Change the burner over to stageĂ1 by pulling plug lÖ. 3. Remove the actuator motor cover. 4. Modify the air volume by turning the adjusting screw on switching camsĂSTĂ1 (see fig. on pageĂ9): H ClockwiseĂĂmore air, H Anti-clockwiseĂĂless air. Please note: Adjust switching camsĂSTĂ1

  • 35 Component summary Component summary (cont.) 5692Ă534ĂGB

  • Viessmann Vitoflame 100 57 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 65 Appendix Maint./service Maint./service Maint./service Maint./service 5692Ă534ĂGB

  • Viessmann Vitoflame 100 29 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner does not start (demand 3Ă× Burner motor faulty Replace burner motor ( lamp illuminates) Actuator faulty (zero volt at terminal 4) Replace actuator Burner does not run and goes into a fault state after approx. 65 s 4Ă× Air pressure switch Check air pressure switch settings and replace switch if necessary pp 4Ă× Earth connection at ionisation cable or electrode Remedy short-circuit Burner motor starts, but a fault 3Ă× Dirty air pressure switch connection Clean connection , shutdown occurs during pre-purge phase 3Ă× A

  • 62 Appendix Commissioning/service report (cont.) Setting and test values Date: By: Set value Maint./service Static pressure mbar max.Ă50Ămbar Supply pressure (flow pressure) j for natural gas E mbar 20ĂĆĂ25 mbar j for natural gas LL mbar 20ĂĆĂ25 mbar tick gas type Nozzle pressure Stage 1 located mbar p set mbar see table on Stage 2 located mbar see table on page 47 set mbar Ionisation current located mA min 5µA set mA min. 5µA Carbon dioxide CO Stage 1 located % by vol. content CO 2 set % by vol. Stage 2 located % by vol. set % by vol. 5692

  • Viessmann Vitoflame 100 5 Initial start-up, inspection and maintenance StepsĂćĂinitial start-up, inspection and maintenance For further instructions on individual steps, see pages indicated. Commissioning steps Inspection steps Maintenance steps Page I M 21. Checking all gas unions for leaksĂ 24. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . M 22. Implementing final testsĂ 24. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5692Ă534ĂGB

  • 42 Parts list Parts list (cont.) 5692Ă534ĂGB

  • Viessmann Vitoflame 100 27 Troubleshooting Diagnostics (cont.) Diagnosis of fault causes Fault code table (red fault lamp) Fault Possible cause 2 x flashing The flame is not established at the end of the safety period 3 x flashing Air pressure switch does not close during pre-purge 4 x flashing Air pressure switch does not open or external light at burner start (after 65 s) 5 x flashing External light during pre-purge or internal device fault 7 x flashing Flame tears off during operation 8 … 17 x flashing Free, no fault code 18 x flashing The air pressure switch opens during pre-purge or operation 19 x flashing Output contact fault Wiring fault External voltag

  • 31 Troubleshooting Diagnostics (cont.) Fault/behaviour of the system Flashing code red Cause Remedy Burner goes from operation into a fault state, when 7Ă× Ionisation current too low (<4 µA) Check position or condition of sensor electrode and change or replace if necessary , flame is already established 7Ă× Electrode body faulty Measure ionisation current and replace ionisation electrode or earth electrode if necessary Burner goes from operation into a fault state, when 7Ă× Ionisation current too low because of incorrect burner settings Correct burner settings

  • Viessmann Vitoflame 100 21 Initial start-up, inspection and maintenance Further details regarding the individual steps (cont.) Checking ignition and ionisation electrodes 90 to 100 kW 125 to 210 kW A Earth electrode B Sensor plate C Ionisation electrode D End plate E Ignition electrode F 8 gas orifices in end plate G Slightly turn the ionisation electrode in accordance with the gap towards the earth electrode H Direct the tip of the ignition electrode towards the edge of the gas orifice 5692Ă534ĂGB

Понравилась статья? Поделить с друзьями:

Это тоже интересно:

  • Инструкция по сверлению отверстий в металле
  • Инструкция по скачиванию видео с ютуба
  • Инструкция по сбору суточной мочи инвитро
  • Инструкция по скандинавской ходьбе с палками для начинающих
  • Инструкция по сбору слюны на кортизол

  • Подписаться
    Уведомить о
    guest

    0 комментариев
    Старые
    Новые Популярные
    Межтекстовые Отзывы
    Посмотреть все комментарии